Services definition |
Citizens can report counter’s reading on his own via many channels: - The hotline 121 that works round-the-clock. - The websites of distribution companies. |
Required documents |
Account references |
Service provision location |
Addresses of service centers of distribution companies (link) |
Duration from order until attainment |
Immediately |
Required fees |
Free from fees |
Services definition |
Enabling the monetary and non-monetary payment of electricity invoices via Fawry Dahab ports and other similar companies all over the country |
Required documents |
Account references |
Service provision location |
Addresses of service centers of distribution companies (link) Addresses of Fawry Dahab ports (link) |
Duration from order until attainment |
Immediately |
Required fees |
Nominal fees according to the provider company |
Services definition |
The subscriber’s request for a statement stating that he is a contractor/conciliator with the distribution company |
Required documents |
- National ID - The beneficiary’s attendance or a one of legal state - A recent electricity invoice |
Procedures |
- The subscriber must complete the statement application form - Paying the prescribed fees - Receiving the statement after verifying the documents |
Service provision location |
Addresses of service centers of distribution companies (p. 30–54) |
Duration from order until attainment |
30 minutes |
Required fees |
30 LE regardless of the tax |
Services definition |
The subscriber’s request for a statement stating his consumption within a period |
Required documents |
- National ID - The beneficiary’s attendance or a one of legal state - A recent electricity invoice |
Procedures |
- The subscriber must complete the statement application form - Paying the prescribed fees - Receiving the statement after verifying the documents |
Service provision location |
Addresses of service centers of distribution companies (p. 30–54) |
Duration from order until attainment |
60 minutes |
Required fees |
30 LE for the first year and then 10 LE for each subsequent year regardless of the tax. |
Services definition |
Electrifying Legal residential premises for which an electrification approval of competent neighborhood’s authority is issued |
Required documents |
- National ID - An electrification approval letter from the neighborhood’s authority - Deed of possession or ownership - License and architectural drawings |
Procedures |
- The subscriber must complete the Electrification form - Conducting on-site inspection and calculating the cost of the electricity inspection and including it for payment - Paying the value of the inspection and the issuance of permits necessary for drilling if requested - Performing the inspection and finishing the application |
Service provision location |
Addresses of service centers of distribution companies (p. 30–54) |
Duration from the order until attainment |
(Application submission = one day), (conducting and preparing the inspection as well as inclusion for payment = 8 days from the date of application), (implementation of the inspection and installation of the counter = 9 days after the payment of the inspection and extracting travel permits) (the total is 18 days) |
Required fees |
The typical value of residential electricity connection is 350 LE/kVA in addition to the value of the counter and any cost for the required technical procedures |
Services definition |
Electrifying investment enterprises |
Required documents |
- National ID - An electrification approval letter from the neighborhood’s authority - Tax card - Commercial register - Deed of possession |
Procedures |
- The subscriber must complete the Electrification form - Conducting on-site inspection and calculating the cost of the electricity inspection and including it for payment - Paying the value of the inspection and the issuance of permits necessary for drilling if requested - Performing the inspection and finishing the application |
Service provision location |
Addresses of service centers of distribution companies (p. 30–54) |
Duration from order until attainment |
(Application submission = one day), (conducting and preparing the inspection as well as inclusion for payment = 8 days from the date of application), (implementation of the inspection and installation of the counter = 9 days after the payment of the inspection and extracting travel permits) (the total is 18 days) |
Required fees |
The typical value of investment electricity connection is 550 LE/kVA in addition to the value of the counter and any cost for the required technical procedures |
These are the entities that follow the Ministry and are affiliated with it under its supervision and are employees of citizens benefit from it directly through the Ministry of Electricity and Energy.